5-2 Earned Value Calculation
Your project has four activities. Below is the current status of each activity.
Activity A was to have cost $160,000 when complete. Its costs so far are $95,000. It is 45% complete.
The activity has completed 5 weeks of a planned 8-week schedule.
Activity B is finished. It finished 2 weeks late. It cost $135,000. And it was planned to have cost $130,000.
Activity C is at the end of week 4 of a planned 8-week effort. It is 40% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.
Activity D is at the end of week 3 of a planned 6-week schedule. It has cost $110,000 so far. It was estimated to cost $200,000 when finished. It is approximately 50% complete.
Using this data, calculate the following.
1.What are the PV, EV, and AC for each of the activities and the complete project?
EVPVAC
A720004275095000
B135000
C4000050000
D55000110000
Project
2.What are the SV, CV, SPI, and CPI for each of the activities and the complete project?
SVCVSPICPI
A
B
C
D
Project
3.Assess the project performance to date? Do you get to have the celebration?
You should focus on the total project but look at the individual activities that have major effects.
Show more
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more